Hornes Road Bridge replacement

Profile photo of the culvert and bridge crossing along Hornes Road.

The Hornes Road Bridge project was completed in October 2024, and the road has reopened to traffic.

 

As part of the municipality’s 2024/25 Capital Plan the Hornes Road bridge is undergoing replacement. This work is necessary to ensure sufficient hydraulic capacity is provided at the crossing. The new structure is a three-sided concrete frame, which includes a naturalized river bottom for improved fish passage. There will also be work on the water/wastewater services to accommodate the new bridge.

Current status

Starting late spring/early summer 2024, contractors began pre-construction. 

Construction began on July 2, 2024, resulting in the road closure. 

For more details, read the public service announcement

Project contact

Kristin Thomas, Project Manager

Email: contactus@311.halifax.ca

Phone: 311