Location: Sackville Drive, from Cobequid Road to Skyridge Avenue
Date: Tuesday, November 30 to Friday, December 3
Time: 7 a.m. to 4 p.m.
Work details: This work is for pavement rehabilitation. This project supports the 2021-25 Regional Council Strategic Priorities Plan to establish a safe and accessible integrated mobility network.
Traffic impact: Lane drops will be in place during this work. Motorists should expect delays and are asked to use alternative routes whenever possible.
Traffic signals at the intersection of Sackville Drive and Skyridge Avenue will be deactivated from 8 a.m. to 12 noon on both days. Traffic personnel will be in place to direct traffic, pedestrians, and cyclists.
**************************************************************************************************
Emplacement : Promenade Sackville, du chemin Cobequid à l’avenue Skyridge
Date : Le mardi 30 novembre à vendredi 3 decembre
Heure : de 7 h à 16 h
Détails des travaux : Ces travaux visent la remise en état de la chaussée. Ce projet appuie le Plan des priorités stratégiques du Conseil régional de 2021-2025 visant à établir un réseau de mobilité intégré qui est sécuritaire et accessible.
Impact sur la circulation : Il y aura des fermetures de voies pendant ces travaux. Les automobilistes doivent s’attendre à des ralentissements, et on leur demande d’emprunter d’autres itinéraires dans la mesure du possible.
Les feux de circulation à l'intersection de la promenade Sackville et de l'avenue Skyridge seront désactivés de 8 h à midi les deux jours. Le personnel de la circulation sera en place pour diriger la circulation, les piétons et les cyclistes.