Bus Stop Location | Nearest Civic Address(es) | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address(es) | Location of Work | Scope of Work | Status |
Hwy 7 Before Circle Dr (8918) | 3293 Hwy 7 | North side of Hwy 7 abutting Civic 3293 | Widen gravel shoulder, new asphalt pad | Completed October 2024 |
Hwy 7 Before Martin Lake Dr (8920) | 3103 Hwy 7 | West side of Hwy 7 abutting Civic 3103 | Widen gravel shoulder, new asphalt pad | Completed October 2024 |
Bus Stop Location | Nearest Civic Address(es) | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address(es) | Location of Work | Scope of Work | Status |
Caldwell Rd After Birchill Dr (2218) | 1720 Birchill Dr | Northeast side of Caldwell Rd abutting Civic 1720 Birchill Dr | New concrete landing pad and sidewalk connection to Birchill Dr | Starting April 2025 |
Caldwell Rd After Cow Bay Rd (6333) | Opposite to 1804 Caldwell Rd | West side of Caldwell Rd near the cemetery | Upgrading shelter pad | Completed September 2024 |
Caldwell Rd After Himmelman Dr (6334) | 49 Sidney Cr | West side of Caldwell Rd after Himmelman Dr abutting Civic 49 Sidney Cr | Upgrading bus pad length | Completed September 2024 |
Caldwell Rd After Thorncrest Ct (6337) | 1881 Caldwell Rd | West side of Caldwell Rd near the elementary school | Upgrading shelter pad | Completed September 2024 |
Caldwell Rd Before Deyoung Dr (2220) | 1622 Caldwell Rd | Northeast side of Caldwell Rd abutting Civic 1622 | New concrete landing pad and sidewalk connection to Deyoung Dr | Starting April 2025 |
Caldwell Rd Before Seabreeze Dr (6340) | 1909 Caldwell Rd | Southwest side of Caldwell Rd near Ocean View Continuing Care Centre | Upgrading shelter pad | Completed September 2024 |
Caldwell Rd Opposite Kaleigh Dr (2219) | 1682 Caldwell Rd | Northeast side of Caldwell Rd abutting Civic 1682 | Concrete landing pad with sidewalk connection to Kaleigh Dr | Starting April 2025 |
Cow Bay Rd Before Caldwell Rd (8674) | 386 Cow Bay Rd | Northwest side of Cow Bay Rd abutting Civic 386 | Concrete landing pad and sidewalk connection to Caldwell Rd intersection | Starting April 2025 |
Heritage Hills Dr Before Cow Bay Rd (8673) | 4 Heritage Hills Dr | Northeast side of Heritage Hills Dr abutting Civic 4 | Concrete landing pad and sidewalk connection to Cow Bay Rd | Completed November 2024 |
Heritage Hills Dr Before Serop Cr (8672) | 1 Serop Cr | Northeast side of Heritage Hills Dr adjacent Civic 1 Serop Cr | Concrete landing pad and sidewalk connection to Serop Cr | Completed November 2024 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Astral Dr After Brookfield Ave (6053) | 198 Astral Dr | East side of Astral Dr abutting Civic 198 | Improvement of existing concrete bus pad and sidewalk | Pending construction 2025 |
Astral Dr At Civic 243 (2351) | 243 Astral Dr | West side of Astral Dr abutting Civic 243 | New bus stop with new concrete pad connecting to new concrete sidewalk, replacing bus stop Astral Dr Before Stratford Dr (6051) | Pending construction 2025 |
Astral Dr Before Brookfield Ave (6054) | 197 Astral Dr | West side of Astral Dr abutting Civic 197 | New concrete bus pad connecting to new concrete sidewalk | Pending construction 2025 |
Astral Dr Before Grenadier Dr (2205) | Opposite of Civic 118 | West side of Astral Dr opposite to Civic 118 | New concrete bus pad connecting to new concrete sidewalk | Pending construction 2025 |
Astral Dr Before Grenadier Dr (6057) | 146 Astral Dr | East side of Astral Dr abutting Civic 146 | Improvement of existing concrete bus pad and sidewalk | Pending construction 2025 |
Astral Dr Before Stratford Dr (6051) | 263 Astral Dr | West side of Astral Dr abutting Civic 263 | Relocation of the stop near Civic 243, removal of existing bus pad and post | Pending construction 2025 |
Brooks Dr At East Preston Rec Centre (8929) | 24 Brooks Dr | West side of Brooks Dr abutting Civic 24 | Relocation to other side of driveway, new concrete pad, connection to multi-use path | Completed December 2024 |
Brooks Dr Opposite East Preston Rec Centre (8769) | 11 Brooks Dr | East side of Brooks Dr abutting Civic 11 | Slight relocation, new elongated concrete pad with pedestrian ramp to access multi-use path on opposite side of street | Completed December 2024 |
Circassion Dr After Ellerslie Cr (2307) | 62 Circassion Cr | West side of Circassion Dr abutting Civic 62 | Relocation of bus stop Circassion Dr Before Ellerslie (6425) after Ellerslie Cr new concrete pad between curb and sidewalk | Completed August 2024 |
Circassion Dr Before Ellerslie (6425) | 80 Circassion Cr | West side of Circassion Dr abutting Civic 80 | Removal of stop, relocation of stop at 62 circassion Dr, concrete removal and grass reinstatement | Pending construction 2025 |
Cole Harbour Rd After Otago Dr (6478) | 915 Cole Harbour Rd | North side of Cole Harbour Rd abutting Civic 915 | Concrete bus pad repair | Completed August 2024 |
Cole Harbour Rd At Civic 1722 (2343) | 1722 Cole Harbour Rd | Northeast side of cole Harbour Rd near civic 1722 | New bus stop created | Completed November 2024 |
Cole Harbour Rd Before Dorothea Dr (6481) | 907 Cole Harbour Rd | North side of Cole Harbour Rd opposite Civic 912 | Shelter replacement | Completed May 2024 |
Cole Harbour Rd Opposite to Pacific Ave (2342) | 1697 Cole Harbour Rd | West side of Cole Harbour Rd near Civic 1697 | New bus stop created | Completed November 2024 |
Flying Cloud Dr Before Gregory Dr (2324) | 204 Flying Cloud Dr | West side of Flying Cloud Dr | New bus stop, new concrete pad and sidewalk | Completed August 2024 |
Forest Hills Pky At Cole Harbour Place (6669) | 51 Forest Hills Pky | East side of Forest Hills Pky abutting Civic 51 | New shelter | Completed March 2024 |
Gregory Dr After Flying Cloud Dr (6792) | 7 Gregory Dr | North side of Gregory Dr abutting Gregory Dr Park | Removal of shelter and old pad, relocation of the bus stop to 204 Flying Cloud Dr | Completed August 2024 |
Hillsboro Dr After Karen Dr (6937) | 111 Hillsboro Dr | West side of Hillsboro Dr after Karen Dr | Consolidation of bus stop to Hillsboro Dr before Karen Dr (2353) | Pending construction 2025 |
Hillsboro Dr After Main St (6934) | N/A | West side of Hillsboro Dr before Karen Dr | Consolidation of bus stop to Hillsboro Dr before Karen Dr (2353) | Pending construction 2025 |
Hillsboro Dr Before Barbara Dr (6935) | 37 Barbara Dr | East side of Hillsboro Dr before Barbara Dr | New concrete pad, curb, and sidewalk repairs. | Pending construction 2025 |
Hillsboro Dr Before Karen Dr (2353) | 8 Karen Dr | West side of Hillsboro Dr before Karen Dr | New bus stop including concrete bus pad, concrete layby and sidewalk to both Karen Dr and Barbara Dr intersection. | Pending construction 2025 |
Hwy 7 After Civic 1776 (8767) | 1776 Hwy 7 | East side of Hwy 7 after the Old Preston Rd intersection | Relocating stop at Hwy 7 after Old Preston Rd, stop will be removed permanently in Feb. 2025 | Completed December 2024 |
Hwy 7 After Glasgow Rd (2340) | 1900 Hwy 7 | South side of Hwy 7 abutting Civic 1900 | New stop with concrete pad, new concrete sidewalk | Completed December 2024 |
Hwy 7 After Old Preston Rd (2339) | Opposite to Civic 1799 | East side of Hwy 7 after the Old Preston Rd intersection | New stop, new concrete pad and sign post in between of the curb and sidewalk, new concrete sidewalk | Completed December 2024 |
Hwy 7 After Upper Governor St (8930) | 1977 Hwy 7 | Northwest side of Hwy 7 abutting Civic 1977 | New concrete bus pad, connection to multi-use path | Completed December 2024 |
Hwy 7 At Civic 1799 (8931) | 1799 Hwy 7 | West side of Hwy 7 abutting Civic 1799 | Relocation, new concrete bus pad, connection to multi-use path | Completed December 2024 |
Hwy 7 Before Glasgow Rd (2341) | 1905 Hwy 7 | North side of Hwy 7 abutting Civic 1905 | New stop with new concrete pad | Completed December 2024 |
Hwy 7 Before Lower Governor St (8768) | 1 Lower Governor St | Southeast side of Hwy 7 adjacent 1 Lower Governor St | Slight relocation of stop, installation of a concrete pad and new sign | Completed December 2024 |
Main St After Cherry Brook Rd (6942) | 10 Cherry Brook Rd | North side of Main St abutting Civic 10 | New shelter | Completed August 2024 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Hudson Way Before Baffin Blvd (6083) | Near the intersection of Hudson Way and Baffin Blvd | North side of Hudson Way | New concrete pad, upgrading accessibility | Pending 2025 construction |
Princess Margaret Blvd After Windmill Rd (8075) | 463 Windmill Rd | North side of Princess Margaret Blvd abutting Civic 463 Windmill Rd | New concrete pad with connecting sidewalk from bus pad to the pedestrian ramp | Pending 2025 construction |
Princess Margaret Blvd At Civic 40 (8071) | 40 Princess Margaret Blvd | West side of Princess Margaret Blvd adjacent to Civic 40 | New concrete pad | Pending 2025 construction |
Princess Margaret Blvd At Civic 55 (8072) | 55 Princess Margaret Blvd | West side of Princess Margaret Blvd adjacent to Civic 55 | New concrete pad, reinstallation of shelter | Pending 2025 construction |
Princess Margaret Blvd Before Windmill Rd (8078) | 461 Windmill Rd | South side of Princess Margaret Blvd abutting Civic 461 Windmill Rd | New concrete pad, upgrading accessibility | Pending 2025 construction |
Thistle St After Beech St (8383) | 74 Thistle St | Southeast side of Thistle St abutting Civic 74 | New concrete pad | Starting April 2025 |
Thistle St After Crichton Park Rd (8384) | 2 Forest Rd | North side of Thistle St near 2 Forest Rd | Upgrading bus pad length | Starting April 2025 |
Thistle St After Mayflower St (8386) | 98 Thistle St | South side of Thistle St abutting Civic 98 | New concrete pad that makes it accessible | Starting April 2025 |
Thistle St Before Crichton Park Rd (8391) | 3 Crichton Park Rd | West side of Crichton Park Rd near Civic 3 | New concrete pad and sidewalk | Starting April 2025 |
Thistle St Before Mayflower St (8388) | 97 Thistle St | North side of Thistle St abutting Civic 97 | New and slightly larger concrete pad | Starting April 2025 |
Thistle St opposite Beech St (8390) | Opposite to 28 Beech St | North side of the Thistle St opposite to 28 Beech St | Slight relocation of the stop and installation of concrete bus pad | Starting April 2025 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Albro Lake Rd Before Chapman St (6020) | 81 Albro Lake Rd | North side of Albro Lake Rd adjacent Civic 85 | Slight relocation, sidewalk repairs, new concrete pad between curb and sidewalk | Pending 2025 construction |
Gregory Dr Before Wildwood Blvd (6794) | Opposite to 14 Gregory Dr | North side of Gregory Dr opposite to Civic 14 | New bench in bus shelter | Completed March 2025 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Barrington St After Cogswell St Bay 3 (6105) | 1990 Barrington St | East side of Barrington St | Concrete bus pad, sidewalk replacement, new bus shelters | Construction started June 2024 |
Barrington St After Duke St Bay 1 (6087) | 1903 Barrington St | West side of Barrington St | Concrete bus pad, sidewalk replacement, new bus shelters | Construction started June 2024 |
Barrington St At Scotia Square Bay 4 (6108) | 1930 Barrington St | East side of Barrington St | Concrete bus pad, sidewalk replacement, new bus shelters | Construction started June 2024 |
Barrington St Before Cogswell Bay 2 (2348) | 1903 Barrington St | West side of Barrington St | Concrete bus pad, sidewalk replacement, new bus shelters | Construction started June 2024 |
Barrington St Before Duke St Bay 5 (6107) | 5201 Duke St | East side of Barrington St | Concrete bus pad, sidewalk replacement, new bus shelters | Construction started June 2024 |
Bell Rd After Robie St (6291) | 1840 Bell Rd | South side of Bell Rd | Slight relocation of bus stop and concrete bus pad extension | Construction started July 2024 |
Inglis St At SMU (6965) | 5932 Inglis St | South side of Inglis St near SMU | Extension of concrete bus pad and shelter pad | Construction started September 2024 |
Inglis St Before Robie St (2322) | 5985 Inglis St | North side of Inglis St near the playground | New bus stop on bumpout, concrete landing pad with tactile directional plates and braille and raised text signage, bus shelter installation | Completed November 2024 |
Inglis St Before Robie St (6966) | Inglis St Elementary School | North side of Inglis St near the elementary school | Removal of stop and concrete pad, consolidation of stops Inglis St Before Robie St (6966) and Inglis St Opposite SMU (6960) and relocation at the location of work | Stop is permanently closed |
Inglis St Opposite SMU (6960) | 5915 Inglis St | North side of Inglis St near Civic 5915 | Removal of stop and concrete pad, consolidation of stops Inglis St Before Robie St (6966) and Inglis St Opposite SMU (6960) | Stop is permanently closed |
Robie St Opposite Binney St (8219) | 1600 Summer St | East side of Robie Street near the cemetery | Slight relocation, new concrete pad between curb and sidewalk | Construction completed October 2024 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Barrington St After Nora Bernard St (6125) | 2170 Barrington St | West side of Barrington St | Removal of stop due to reconfiguration of Barrington St | Completed October 2024 |
Barrington St After Roundabout (2344) | 2242 Barrington St | East side of Barrington St | New stop, new concrete pad | Completed November 2024 |
Barrington St After Upper Water St (2347) | 2089 Upper Water St | North side of street | New stop, new concrete pad | Completed December 2024 |
Barrington St Before Nora Bernard St (6104) | 5221 Barrington St | West side of Barrington St | Relocation of stop, new concrete bus pad | Construction started October 2024 |
Barrington St Before Roundabout (2345) | 2202 Upper Water St | East side of Upper Water St | New stop, new concrete pad | Completed October 2024 |
Barrington St Before Upper Water St (2346) | 2021 Brunswick St | West side of Barrington St | New stop, new concrete pad | Construction started October 2024 |
Duffus St After Novalea Dr (6583) | 5521/5515 Duffus St | North side of Duffus St abutting Civic 5521/5515 | Shelter replacement | Completed October 2024 |
Quinpool Rd Before Windsor St (8261) | 6067 Quinpool Rd | North side of Quinpool Rd adjacent to the playground | Installation of larger shelter | Completed July 2024 |
Robie St Before Cabot St (8203) | 3468 Robie St | Southwest side of Robie St abutting Civic 3468 | Shelter replacement | Completed October 2024 |
Windsor St After Connaught Ave (8551) | 3628 Windsor St | South side of Windsor St abutting Civic 3628 | Concrete pad extension | Completed December 2024 |
Windsor St Before Maxwell Ave (8565) | 3380 Windsor St | South side of Windsor St abutting Civic 3380 | Slight relocation, new concrete pad between curb and sidewalk | Completed December 2024 |
Windsor St Opposite London St (8572) | 2901 Windsor St | Northeast side of Windsor St abutting Civic 2901 | Shelter replacement | Completed October 2024 |
Young St After Monaghan Dr (8629) | 6141 Young St | Northwest side of Young St abutting Civic 6141 | Shelter replacement | Completed July 2024 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Joseph Howe Dr After Scot St (2325) | 3601 Joseph Howe Dr | East side of Joseph Howe Dr near the Superstore | New concrete pad between curb and sidewalk, new shelter pad and shelter behind the sidewalk | Pending 2025 construction |
Joseph Howe Dr Before Abbott Dr (6979) | Opposite and North of 7165 Abbott Dr | West side of Joseph Howe Dr south of Hwy 102 overpass | New concrete shelter pad and shelter behind sidewalk | Completed March 2025 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Bedford Hwy After Torrington Dr (6279) | 2 Torrington Dr | South side of Bedford Hwy adjacent Civic 2 Torrington Dr | Shelter replacement | Completed 2024 |
Rosedale Ave After Alex St (8249) | 61 Rosedale Ave | North side of Rosedale Ave near Civic 61 | Slight relocation with new bus pad | Complete August 2024 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Greystone Dr After Cobalt Walk (6798) | 160 Lavender Walk | At the cul-de-sac of the Greystone Dr near Civic 160 Lavender Walk | New concrete pad between curb and sidewalk | Completed August 2024 |
Purcells Cove Rd After Dingle Rd (8118) | 1452 Purcells Cove Rd | East side of Purcells Cove Rd abutting Civic 1452 | Shelter replacement | Completed August 2024 |
Purcells Cove Rd After Sailboat Ln (8122) | Opposite 1255 Purcells Cove Rd | North side of Purcells Cove Rd near Reserve Rd | Shelter replacement | Completed September 2024 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Chain Lake Dr At Civic 209 (6394) | 209 Chain Lake Dr | West side of Chain Lake Dr abutting Civic 209 | Concrete pad extension | Completed October 2024 |
Julius Blvd Before Dugger McNeil Dr (2315) | 125 Julius Blvd | South side of Julius Blvd adjacent Civic 125 | New bus stop, new concrete pad between curb and sidewalk | Completed October 2024 |
Julius Blvd Before Dugger McNeil Dr (2317) | 82 Julius Blvd | North side of Julius Blvd adjacent Civic 85 | New bus stop, new concrete pad between curb and multi-use path | Completed October 2024 |
Maplewood Dr Before St Margarets Bay Rd (7180) | 10 Maplewood Dr | South side of Maplewood Dr after the trail | Slight relocation of bus stop with new concrete pad | Completed December 2024 |
St Margarets Bay Rd After Clearwater Dr (6175) | 1 Devonshire Dr | North Side of St Margarets Bay Rd after Devonshire Dr and St Margarets Bay Rd Intersection | New concrete pad and pedestrian ramp to intersection | Completed October 2024 |
St Margarets Bay Rd After Raines Mill Rd (2328) | 2 Raines Mill Rd | North side of St Margarets Bay Rd abutting 2 Raines Mill Rd | New bus stop with new concrete pad between curb and sidewalk, replacing bus stop St Margarets Bay Rd Before Raines Mill Rd (6180) | Completed January 2025 |
St Margarets Bay Rd at Civic 1917 (2330) | 1917 St Margarets Bay Rd | North side of St Margarets Bay Rd abutting Civic 1917 | New bus stop with new concrete pad between the curb and the sidewalk, replacing bus stop St Margarets Bay Rd At Civic 1939 (6149) | Pending 2025 construction |
St Margarets Bay Rd At Civic 1922 (6170) | 1928 St Margarets Bay Rd | South side of St Margarets Bay road near Civic 1928 | New concrete pad between curb and sidewalk | Pending 2024 construction |
St Margarets Bay Rd At Civic 1939 (6149) | 1939 St Margarets Bay Rd | North side of St Margarets Bay Rd near Civic 1917 | Removal of bus stop, new location of bus stop to further east side of St Margarets Bay Rd at Civic 1917 (2330) | Stop is permanently closed |
St Margarets Bay Rd Before Raines Mill Rd (6180) | 1403 Lakeside Dr | North side of St Margarets Bay Rd near Civic 1403 Lakeside Dr | Removal of bus stop, new location of bus stop at St Margarets Bay Rd After Raines Mill Rd (2328) | Stop is permanently closed |
St Margarets Bay Rd Before Sheppards Run (6157) | 438 Sheppards Run | South side of St Margarets Bay Rd adjacent 438 Sheppards Run | Shelter replacement | Completed October 2024 |
St Margarets Bay Rd Opposite Boylan Ln (6164) | 1370 St Margarets Bay Rd | South side of St Margarets Bay Rd abutting Civic 1370 | New concrete bus pad and new sidewalk from Raines Mill Rd to Oliver St, connecting shelter pad to an accessible pedestrian route | Completed January 2025 |
Susie Lake Cr Before Julius Blvd (2313) | 420 Susie Lake Cr | North side of Susie Lake Cr opposite Civic 420 | New concrete pad between curb and sidewalk, concrete shelter pad, and shelter | Completed March 2024 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Beaver Bank Rd After Welkin Dr (8755) | 352 Beaver Bank Rd | West side of Beaver Bank Rd opposite Civic 345 | New signpost, concrete pad, and sidewalk connection to intersection at Welkin Dr | Completed 2024 |
Beaver Bank Rd Before Welkin Dr (8713) | 343 Beaver Bank Rd | East side of Beaver Bank Rd near Civic 343 | Relocation bus stop forward ~10m, concrete pad increase, installation of signpost | Completed May 2024 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Cobequid Rd After Freer Ln (6434) | 191 Cobequid Rd | East side of Cobequid Rd near Civic 191 | New shelter pad | Completed December 2023 |
Cobequid Rd After Maple Grove Dr (6431) | 450 Cobequid Rd | West side of Cobequid Rd near Civic 450 | New shelter pad | Completed December 2024 |
Cobequid Rd Before Maple Grove Dr (6441) | 473 Cobequid Rd | East side of Cobequid Rd near Civic 477 | Relocation of the stop to Civic 477, stop will be closed permanently from February | Completed December 2024 |
Cobequid Rd After Maple Grove Dr (2349) | 477 Cobequid Rd | East side of Cobequid Rd near Civic 477 | New bus stop with new concrete pad and connection to new concrete sidewalk, replacing bus stop Cobequid Rd Before Maple Grove Dr (6441) | Completed December 2024 |
First Lake Dr After Civic 192 (6683) | 192 First Lake Dr | North side of First Lake Dr near Civic 192 | New sidewalk connection to the concrete pad | Completed July 2024 |
Sackville Dr Before Armoyan Dr (7313) | 300 Sackville Dr | West side of Sackville Dr abutting Civic 300 | Shelter replacement | Completed October 2024 |
Sackville Terminal Bay 4 (8960) | Sackville Terminal | Sackville Terminal | Shelter replacement | Completed October 2024 |
Stokil Dr After Grennan Dr (8354) | 86 Grennan Dr | West side of Stokil Dr near Civic 86 Grennan Dr | Concrete pad replacement | Completed September 2024 |
Stokil Dr After Grennan Dr (8356) | 253 Stokil Dr | East side of Stokil Dr near Civic 1 Armcrest Dr | Slight relocation to Civic 1 Armcrest Dr, new concrete pad between curb and sidewalk | Completed September 2024 |
Stokil Dr After Sampson Dr (8355) | 2 Sampson Dr | North side of Stokil Dr near Civic 2 Sampson Dr | Concrete pad replacement | Completed September 2024 |
Stokil Dr Before Smokey Dr (8358) | 241 Smokey Dr | West side of Stokil Dr adjacent to elementary school | Concrete pad replacement | Completed September 2024 |
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
---|---|---|---|---|
Bus Stop Location | Nearest Civic Address | Location of Work | Scope of Work | Status |
Bedford Hwy After Charlotte Ln (6287) | 587 Bedford Hwy | East side of Bedford Hwy near Civic 587 | New concrete bus pad, new shelter with shelter pad, sidewalk connection to Charlotte Ln intersection | Pending 2025 construction |
Bedford Hwy After Shaunslieve Dr (6234) | 34 Shaunslieve Dr | West side of Bedford Hwy near Civic 34 Shaunslieve Dr | New concrete bus pad, shelter replacement, sidewalk connection to Shaunslieve Dr intersection | Pending 2025 construction |
Bedford Hwy Before Spring St (6249) | 1326 Bedford Hwy | Northwest side of Bedford Hwy abutting Civic 1326 | Shelter replacement | Completed July 2024 |
Bedford Hwy Before Union St (6228) | 1488 Bedford Hwy | North side of Bedford Hwy abutting Civic 1488 | Shelter replacement | Completed January 2024 |
Broad St Before Larry Uteck Blvd (2027) | 51 Jam Ln | North side of Broad St adjacent Civic 51 Jam Ln | New concrete shelter pad and shelter | Construction starting November 2024 |
Larry Uteck Blvd After Kearney Lake Rd (6298) | 1000 Larry Uteck Blvd | South side of Larry Uteck Blvd abutting Civic 1000 | New concrete bus pad, shelter, sidewalk connection, and RA-5 crosswalk | Completed January 2024 |
Larry Uteck Blvd Before Abbington Ave (7022) | 29 Abbington Ave | Northeast side of Larry Uteck Blvd adjacent Civic 29 Abbington Ave | New bus pad, sidewalk connection, and RA-5 crosswalk | Completed August 2024 |
Larry Uteck Blvd Before Belle St (7027) | 3 Belle St | Southwest side of Larry Uteck Blvd adjacent Civic 3 Belle St | New bus pad, sidewalk connection, and RA-5 crosswalk | Completed August 2024 |